Start: | January 13, 2009 |
Finish: | April 1, 2009 |
Report Date: | March 15, 2009 |
|
|
WBS | Name | Start | Finish | Work | Priority | Complete | Cost |
---|---|---|---|---|---|---|---|
1 | Requirements Elicitation | Jan 13 | Feb 10 | 143d | |||
1.1 | Preliminary Requirements | Jan 13 | Jan 29 | 78d | 100% | ||
1.2 | System Requirements Specification | Jan 23 | Feb 10 | 65d | |||
1.2.1 | Project Vision/Goals | Jan 23 | Feb 10 | 13d | 100% | ||
1.2.2 | Functional Requirements | Jan 23 | Feb 10 | 13d | 100% | ||
1.2.3 | Non-Functional Requirements | Jan 23 | Feb 10 | 13d | 100% | ||
1.2.4 | Interface Requirements | Jan 23 | Feb 10 | 13d | 100% | ||
1.2.5 | Data Requirements | Jan 23 | Feb 10 | 13d | 100% | ||
2 | System Analysis and Design | Feb 11 | Feb 20 | 32d | |||
2.1 | Sequence Diagrams | Feb 11 | Feb 13 | 8d | 69% | ||
2.2 | Class Diagram | Feb 11 | Feb 20 | 8d | 60% | ||
2.3 | Component Diagram | Feb 11 | Feb 16 | 8d | 50% | ||
2.4 | Activity Diagram | Feb 11 | Feb 20 | 8d | 76% | ||
3 | Implementation and Testing | Feb 23 | Mar 24 | 48d 5h | |||
3.1 | Design core UI | Feb 23 | Mar 16 | 15d 7h | 70% | ||
3.2 | Refine UI | Mar 16 | Mar 24 | 5d 7h | 0% | ||
3.3 | User management | Mar 16 | Mar 19 | 6d 2h | 61% | ||
3.4 | Shipment creation | Mar 16 | Mar 20 | 7d | 28% | ||
3.5 | Shipment receipt | Mar 16 | Mar 20 | 3d 3h | 0% | ||
3.6 | Reports | Mar 16 | Mar 23 | 4d 5h | 0% | ||
3.7 | Special feature 1 | Mar 20 | Mar 23 | 1d 7h | 0% | ||
3.8 | Special feature 2 | Mar 20 | Mar 23 | 2d | 0% | ||
3.9 | Add warehouse, shipping/rental rules | Mar 20 | Mar 23 | 1d 5h | 0% | ||
4 | UI + Functionality Demo | Mar 31 | Mar 31 | 7d | 0% |